Within the framework of a consortium of companies*, Clemessy is carrying out for EDF Production Energie Insulaire, the low- and high-voltage installations along with the overall monitoring & control facilities for the new Diesel power plants in the French Overseas Departments (DOM) and Corsica.

This contract which was won in 2008 is a major reference for Clemessy as it is the largest contract in the Group’s history.

In the French Overseas Departments (DOM)

The contract covers the construction of 3 power plants with twelve 18.9 MW generator sets, i.e. a production capacity of 680 MW.

For each of the DOM power plants, Clemessy is carrying out the work of designing and integrating :

  • the power plant’s electricity supply grid and connection to the island grid
  • the power plants’ monitoring & control system and their commons
  • the security of the site (fire, peripheral protection, communications)
  • the direct current system and UPS systems
  • the emergency generators

 

The equipment installed is performing particularly well from an industrial and environmental point of view.

In Corsica

At the Corsican Lucciana B power plant, Clemessy is carrying out the design and integration work for :

  • the equipment connecting the power plants to the supply grid
  • the power plants’ monitoring & control system and their communs
  • the direct current system and UPS systems

WIthin the framework of this contract, Clemessy provides training for several hundred operators, maintenance and supervisory staff in the fields of high-voltage, monitoring & control and low-voltage installations.